Performance Test for Termopacífico Generation Plant

Chile - Copiapó
Verbundene Lösungen
Auftraggeber Prime Energía
Standort Copiapó, Atacama, Chile
Laufzeit 2021
Leistung 96 MW (60 Units of 1.6 MW each)

Project Description

Performance tests for the Termopacífico power plant, a backup generation plant consisting of eighty-three diesel generators.

Services Provided

Performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ISO 3046 and ISO 15500.