Auftraggeber | Prime Energía |
---|---|
Standort | Vallenar, Región de Atacama, Chile |
Laufzeit | 2021 |
Leistung | 112MW |
Performance Test for Pajonales power plant. Pajonales is a backup plant conformed by 42 diesel MTU generator sets (56 MTU diesel motors of 1,8 MW each).
Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ISO 3046 and ISO 15500.